• SMASH/Muir Water Intrusion Project Update May 31, 2024

    Posted by Esmeralda Careaga on 5/31/2024 12:40:00 PM

    The Smash/Muir Water Intrusion Project represents a comprehensive campus-wide endeavor aimed at revitalizing and enriching our educational infrastructure. This initiative involves a complete revamp of roofing systems, stucco, windows, doors, and flooring, alongside substantial structural enhancements. A crucial component of this renovation is ensuring that all classrooms and restrooms meet Americans with Disabilities Act compliance standards, integrating a range of additional improvements. We're pleased to announce that Buildings A, B, C, and D have received Division of the State Architect (DSA) approval, with Construction Change Directives submitted for each building awaiting further review and approval by the DSA.

    An essential goal of this project is to guarantee the comprehensive waterproofing and sealing of the entire campus. This entails meticulous care to uphold the integrity of building envelopes, ensuring that all structures are impermeable to water infiltration and environmentally sound. This precaution is crucial for the durability of campus buildings and the safety and well-being of its occupants.

    The goal is to finish the project in preparation for the fall 2025 academic session, providing students with a revitalized, secure, and cutting-edge educational setting.

    Project Progress:

    The construction of the mock up to showcase the waterproof system is ongoing.

    The concrete pour for the footings of Buildings A, C, and D has been completed.

    Installation of bottom rebar is currently ongoing for Building B.

    The removal of exterior stucco across the entire campus is in progress.

    Installation of additional scaffolding for the roof and surrounding plaster access is ongoing.

    For more information on Muir/SMASH campus projects, please contact Senior Project Manager for Facility Improvement Projects Kay Khadem at kkhadem@smmusd.org.

    Comments (-1)
  • SMASH/Muir Water Intrusion Project Update May 10, 2024

    Posted by Esmeralda Careaga on 5/10/2024 5:40:00 PM

    The Smash/Muir Water Intrusion Project represents a comprehensive campus-wide endeavor aimed at revitalizing and enriching our educational infrastructure. This initiative involves a complete revamp of roofing systems, stucco, windows, doors, and flooring, alongside substantial structural enhancements. A crucial component of this renovation is ensuring that all classrooms and restrooms meet Americans with Disabilities Act compliance standards, integrating a range of additional improvements. We're pleased to announce that Buildings A, B, C, and D have received Division of the State Architect (DSA) approval, with Construction Change Directives submitted for each building awaiting further review and approval by the DSA.

    An essential goal of this project is to guarantee the comprehensive waterproofing and sealing of the entire campus. This entails meticulous care to uphold the integrity of building envelopes, ensuring that all structures are impermeable to water infiltration and environmentally sound. This precaution is crucial for the durability of campus buildings and the safety and well-being of its occupants.

    The goal is to finish the project in preparation for the fall 2025 academic session, providing students with a revitalized, secure, and cutting-edge educational setting.

    Project Progress Update:

    • Concrete pouring for the footings of Buildings C & D is scheduled for Tuesday, May 14 and Wednesday, May 15, 2024.
    • Ongoing installation of bottom rebar for all buildings.
    • Active pull tests and inspections of rebar across all buildings.
    • Progressing removal of exterior stucco across the entire campus.
    • Layout, saw cutting and demolition for new structural footings underway for all buildings.
    • Continuation of excavation and removal operations for the new structural footings of all buildings.
    • Completion of exterior HVAC units’ removal.
    • Ongoing installation of additional scaffolding for the roof and surrounding plaster access.

     

    Thank you for your ongoing patience and understanding during the construction process.

    For more information on Muir/SMASH campus projects, please contact Senior Project Manager for Facility Improvement Projects Kay Khadem at kkhadem@smmusd.org.

    Comments (-1)
  • SMASH/Muir Water Intrusion Project Update May 3, 2024

    Posted by Esmeralda Careaga on 5/3/2024 4:10:00 PM

    The Smash/Muir Water Intrusion Project represents a comprehensive campus-wide endeavor aimed at revitalizing and enriching our educational infrastructure. This initiative involves a complete revamp of roofing systems, stucco, windows, doors, and flooring, alongside substantial structural enhancements. A crucial component of this renovation is ensuring that all classrooms and restrooms meet Americans with Disabilities Act compliance standards, integrating a range of additional improvements. We're pleased to announce that Buildings A, B, C, and D have received Division of the State Architect (DSA) approval, with Construction Change Directives submitted for each building awaiting further review and approval by the DSA.

    An essential goal of this project is to guarantee the comprehensive waterproofing and sealing of the entire campus. This entails meticulous care to uphold the integrity of building envelopes, ensuring that all structures are impermeable to water infiltration and environmentally sound. This precaution is crucial for the durability of campus buildings and the safety and well-being of its occupants.

    The goal is to finish the project in preparation for the fall 2025 academic session, providing students with a revitalized, secure, and cutting-edge educational setting.

    Project Progress:

    A. The ongoing process of removing exterior stucco throughout the entire campus is underway.

    B. Progress is being made on the layout, saw cutting, and demolition required for the installation of new structural footings in all buildings.

    C. The ongoing processes involve excavating and removing the old structural footings for all buildings.

    D. The rebar installation is scheduled to begin the week of April 22, 2024.

    F. Removal of exterior Heating Ventilation and Air Conditioning units is also in progress.

    Thank you for your ongoing patience and understanding during the construction process.

    For more information on Muir/SMASH campus projects, please contact Senior Project Manager for Facility Improvement Projects Kay Khadem at kkhadem@smmusd.org.

    Comments (-1)
  • SMASH/Muir Water Intrusion Project Update April 26, 2024

    Posted by Esmeralda Careaga on 4/26/2024 1:40:00 PM

    The Smash/Muir Water Intrusion Project represents a comprehensive campus-wide endeavor aimed at revitalizing and enriching our educational infrastructure. This initiative involves a complete revamp of roofing systems, stucco, windows, doors, and flooring, alongside substantial structural enhancements. A crucial component of this renovation is ensuring that all classrooms and restrooms meet Americans with Disabilities Act compliance standards, integrating a range of additional improvements. We're pleased to announce that Buildings A, B, C, and D have received Division of the State Architect (DSA) approval, with Construction Change Directives submitted for each building awaiting further review and approval by the DSA.

    An essential goal of this project is to guarantee the comprehensive waterproofing and sealing of the entire campus. This entails meticulous care to uphold the integrity of building envelopes, ensuring that all structures are impermeable to water infiltration and environmentally sound. This precaution is crucial for the durability of campus buildings and the safety and well-being of its occupants.

    The goal is to finish the project in preparation for the fall 2025 academic session, providing students with a revitalized, secure, and cutting-edge educational setting.

    Project Progress:

    A. The ongoing process of removing exterior stucco throughout the entire campus is underway.

    B. Progress is being made on the layout, saw cutting, and demolition required for the installation of new structural footings in all buildings.

    C. The ongoing processes involve excavating and removing the old structural footings for all buildings.

    D. The rebar installation is scheduled to begin the week of April 22, 2024.

    F. Removal of exterior Heating Ventilation and Air Conditioning units is also in progress.

    Thank you for your ongoing patience and understanding during the construction process.

    For more information on Muir/SMASH campus projects, please contact Senior Project Manager for Facility Improvement Projects Kay Khadem at kkhadem@smmusd.org.

    Comments (-1)
  • SMASH/Muir Water Intrusion Project Update April 19, 2024

    Posted by Esmeralda Careaga on 4/19/2024 1:20:00 PM

    The Smash/Muir Water Intrusion Project represents a comprehensive campus-wide endeavor aimed at revitalizing and enriching our educational infrastructure. This initiative involves a complete revamp of roofing systems, stucco, windows, doors, and flooring, alongside substantial structural enhancements.

    A crucial component of this renovation is ensuring that all classrooms and restrooms meet Americans with Disabilities Act compliance standards, integrating a range of additional improvements. We're pleased to announce that Buildings A, B, C, and D have received Division of the State Architect (DSA) approval, with Construction Change Directives submitted for each building awaiting further review and approval by the DSA.

    An essential goal of this project is to guarantee the comprehensive waterproofing and sealing of the entire campus. This entails meticulous care to uphold the integrity of building envelopes, ensuring that all structures are impermeable to water infiltration and environmentally sound. This precaution is crucial for the durability of campus buildings and the safety and well-being of its occupants.

    The goal is to finish the project in preparation for the fall 2025 academic session, providing students with a revitalized, secure, and cutting-edge educational setting.

    Project Progress:

    A. The ongoing process of removing exterior stucco throughout the entire campus is underway.

    B. Progress is being made on the layout, saw cutting, and demolition required for the installation of new structural footings in all buildings.

    C. The ongoing processes involve excavating and removing the old structural footings for all buildings.

    D. The rebar installation is scheduled to begin the week of April 22, 2024.

    F. Removal of exterior Heating Ventilation and Air Conditioning units is also in progress.

    Thank you for your ongoing patience and understanding during the construction process.

    For more information on Muir/SMASH campus projects, please contact Senior Project Manager for Facility Improvement Projects Kay Khadem at kkhadem@smmusd.org.

    Comments (-1)
  • SMASH/Muir Water Intrusion Project Update April 12, 2024

    Posted by Esmeralda Careaga on 4/12/2024 4:25:00 PM

    The Smash/Muir Water Intrusion Project represents a comprehensive campus-wide endeavor aimed at revitalizing and enriching our educational infrastructure. This initiative involves a complete revamp of roofing systems, stucco, windows, doors, and flooring, alongside substantial structural enhancements. A crucial component of this renovation is ensuring that all classrooms and restrooms meet Americans with Disabilities Act compliance standards, integrating a range of additional improvements. We're pleased to announce that Buildings A, B, C, and D have received Division of the State Architect (DSA) approval, with Construction Change Directives submitted for each building awaiting further review and approval by the DSA.

    An essential goal of this project is to guarantee the comprehensive waterproofing and sealing of the entire campus. This entails meticulous care to uphold the integrity of building envelopes, ensuring that all structures are impermeable to water infiltration and environmentally sound. This precaution is crucial for the durability of campus buildings and the safety and well-being of its occupants.

    The goal is to finish the project in preparation for the fall 2025 academic session, providing students with a revitalized, secure, and cutting-edge educational setting.

    Project Progress:

    • The ongoing process of removing exterior stucco throughout the entire campus is underway.
    • Progress is being made on the layout, saw cutting, and demolition required for the installation of new structural footings in all buildings.
    • Ongoing excavation and removal activities are underway for the installation of new structural footings in all buildings. 
    • The removal of exterior Heating Ventilation and Air Conditioning units is currently underway.

    Thank you for your ongoing patience and understanding during the construction process.

    For more information on Muir/SMASH campus projects, please contact Senior Project Manager for Facility Improvement Projects Kay Khadem at kkhadem@smmusd.org.

    Comments (-1)
  • SMASH/Muir Water Intrusion Project Update March 28, 2024

    Posted by Esmeralda Careaga on 3/29/2024 7:25:00 PM

    The Santa Monica Alternative School House/John Muir Elementary School Water Intrusion Project is a comprehensive campus-wide endeavor aimed at revitalizing and improving our educational facilities. This initiative involves a thorough renovation of the roofing system, stucco, windows, doors, and flooring, along with substantial structural enhancements. A crucial aspect of this project is ensuring that all classrooms and restrooms adhere to Americans with Disabilities Act compliance standards, while also integrating various other enhancements. We have obtained Division of the State Architect (DSA) approval for buildings A, B, C, and D.

    An essential goal of this project is to guarantee the comprehensive waterproofing and sealing of the entire campus. This entails meticulous care to uphold the integrity of building envelopes, ensuring that all structures are impermeable to water infiltration and environmentally sound. This precaution is crucial for the durability of campus buildings and the safety and well-being of its occupants.

    The goal is to finish the project in preparation for the fall 2025 academic session, providing students with a revitalized, secure, and cutting-edge educational setting.

    Project Progress:

    • The process of removing the exterior stucco has continued.
    • The scanning, layout, saw cutting, and demolition activities are currently underway to facilitate the installation of new structural footings in Buildings A, C, and D. These tasks began after receiving approvals from the DSA and are expected to persist until mid-April 2024.
    • The excavation and off-haul processes for the new structural footings in Buildings A, C, and D are currently in progress and are projected to be finished by early May 2024.
    • Presently, we are undertaking mold remediation on impacted wood as part of our quality control protocols.

    Thank you for your ongoing patience and understanding during the construction process.

    For more information on Muir/SMASH campus projects, please contact Senior Project Manager for Facility Improvement Projects Kay Khadem at kkhadem@smmusd.org.

     

     

     

    Comments (-1)
  • SMASH/Muir Water Intrusion Project Update March 22, 2024

    Posted by Esmeralda Careaga on 3/22/2024 12:35:00 PM

    The Santa Monica Alternative School House/John Muir Elementary School Water Intrusion Project is a comprehensive campus-wide endeavor aimed at revitalizing and improving our educational facilities. This initiative involves a thorough renovation of the roofing system, stucco, windows, doors, and flooring, along with substantial structural enhancements. A crucial aspect of this project is ensuring that all classrooms and restrooms adhere to Americans with Disabilities Act compliance standards, while also integrating various other enhancements. We have obtained Division of the State Architect (DSA) approval for buildings A, C, and D and are currently awaiting DSA approval for building B.

    An essential goal of this project is to guarantee the comprehensive waterproofing and sealing of the entire campus. This entails meticulous care to uphold the integrity of building envelopes, ensuring that all structures are impermeable to water infiltration and environmentally sound. This precaution is crucial for the durability of campus buildings and the safety and well-being of it's occupants.

    The goal is to finish the project in preparation for the fall 2025 academic session, providing students with a revitalized, secure, and cutting-edge educational setting.

    Project Progress:

    • The process of removing the exterior stucco has commenced.
    • The scanning, layout, saw cutting, and demolition activities are currently underway to facilitate the installation of new structural footings in Buildings A, C, and D. These tasks began after receiving approvals from the DSA and are expected to persist until mid-April 2024.
    • The excavation and off-haul processes for the new structural footings in Buildings A, C, and D are currently in progress and are projected to be finished by early May 2024.
    • Presently, we are undertaking mold remediation on impacted wood as part of our quality control protocols.

    Thank you for your ongoing patience and understanding during the construction process.

    For more information on Muir/SMASH campus projects, please contact Senior Project Manager for Facility Improvement Projects Kay Khadem at kkhadem@smmusd.org.

     

     

     

     

    Comments (-1)
  • SMASH/Muir Water Intrusion Project Update March 15, 2024

    Posted by Esmeralda Careaga on 3/15/2024 12:55:00 PM

    The Santa Monica Alternative School House/John Muir Elementary School Water Intrusion Project is a comprehensive campus-wide endeavor aimed at revitalizing and improving our educational facilities. This initiative involves a thorough renovation of the roofing system, stucco, windows, doors, and flooring, along with substantial structural enhancements. A crucial aspect of this project is ensuring that all classrooms and restrooms adhere to Americans with Disabilities Act compliance standards, while also integrating various other enhancements. We have obtained Division of the State Architect (DSA) approval for buildings A&D and are currently awaiting DSA approval for buildings C&B.

    An essential goal of this project is to guarantee the comprehensive waterproofing and sealing of the entire campus. This entails meticulous care to uphold the integrity of building envelopes, ensuring that all structures are impermeable to water infiltration and environmentally sound. This precaution is crucial for the durability of campus buildings and the safety and well-being of its occupants.

    The goal is to finish the project in preparation for the fall 2025 academic session, providing students with a revitalized, secure, and cutting-edge educational setting.

    Project Progress:

    • Preparatory actions such as scanning, layout planning, saw cutting, and demolition have commenced for the placement of new structural footings in Buildings A, C, and D. Approval from the DSA has been obtained for these initiatives. These preparatory tasks are slated to persist until mid-April 2024.
    • Excavation and removal of excess soil for the new structural footings in Buildings A, C, and D are currently in progress and anticipated to conclude by early May 2024.
    • Ongoing efforts to remediate mold on affected lumber are currently underway and are being managed as part of our quality control protocols.

    Thank you for your ongoing patience and understanding during the construction process.

    For more information on Muir/SMASH campus projects, please contact Senior Project Manager for Facility Improvement Projects Kay Khadem at kkhadem@smmusd.org.

     

     

     

     

     

    Comments (-1)
  • SMASH/Muir Water Intrusion Project Update (March 8, 2024)

    Posted by Esmeralda Careaga on 3/8/2024 3:10:00 PM

    The Santa Monica Alternative School House/John Muir Elementary School Water Intrusion Project is a comprehensive campus-wide endeavor aimed at revitalizing and improving our educational facilities. This initiative involves a thorough renovation of the roofing system, stucco, windows, doors, and flooring, along with substantial structural enhancements. A crucial aspect of this project is ensuring that all classrooms and restrooms adhere to Americans with Disabilities Act compliance standards, while also integrating various other enhancements. We have obtained Division of the State Architect (DSA) approval for buildings A&D and are currently awaiting DSA approval for buildings C&B.

    An essential goal of this project is to guarantee the comprehensive waterproofing and sealing of the entire campus. This entails meticulous care to uphold the integrity of building envelopes, ensuring that all structures are impermeable to water infiltration and environmentally sound. This precaution is crucial for the durability of campus buildings and the safety and well-being of it's occupants.

    The goal is to finish the project in preparation for the fall 2025 academic session, providing students with a revitalized, secure, and cutting-edge educational setting.

    Project Progress:

    • Interior Demolition and Mold Removal: Remediation efforts for mold on lumber are currently underway.
    • Exterior Stairs Demolition: The demolition of the exterior stairs has been completed, and a temporary staircase has been installed in place of the original.
    •  Exterior and Interior Footings: Following approval from the DSA, activities such as scanning, layout, saw cutting, and demolition to prepare for the new structural footing in Buildings A, C, & D have commenced. These activities are anticipated to continue until mid-April 2024.
    • Excavation: Excavation and off-haul preparations for the new structural footing in Building D are set to commence on March 15, 2024.

    Thank you for your ongoing patience and understanding during the construction process.

    For more information on Muir/SMASH campus projects, please contact Senior Project Manager for Facility Improvement Projects Kay Khadem at kkhadem@smmusd.org.