MMHS Construction Update: Middle School Building almost ready
Posted by Chris Clonts on 8/2/2019 11:15:00 AM
MIDDLE SCHOOL BUILDING
- The building (above), comprising 12 classrooms and three sets of boys/girls restrooms, is 90% complete.
- Carpet and tile were installed, as was adaptable furniture (shown at left) such as multi-configuration desks, chairs, cabinets, ceiling-mounted video projectors and whiteboards.
- The elevator tower is 80% complete, and the elevator cab is scheduled to arrive next week.
- The final exterior walkways, seat walls, landscape, and exterior painting are in progress and should be complete by the scheduled ribbon cutting (August 13 at 12:30 p.m.).
ADMINISTRATION BUILDING
- This new building, shown here (Middle School Building is on the right), is progressing rapidly, as many main structural components are now in.
All vertical concrete walls have been poured and completed. - The concrete slab on grade for segment B of the new building has been poured.
- Structural steel has been delivered to the site and nearly all of the steel for one segment of the building has been erected and bolted in place.
- The metal deck for the second floor has been placed. The work to place lightweight concrete will begin in a few weeks.
- The building (above) is really taking shape with the new "V" columns installed at the main entrance, creating quite a view as one arrives to the site via Morning View Drive.