Preparing for Return to School Fall 2021
Posted by Kelcey Davis on 8/16/2021 2:00:00 PM
The Facilities team has been preparing the campus for safe, in-person learning. Below is an update on the many projects that are completed, in progress, or set to begin in the future.
Painting Project
The first thing you will see when returning to school is that the exterior was painted. Exterior stucco was painted SMMUSD standard off white/alabaster grey eggshell gloss level. This project was completed and on schedule on July 10th. This project complimented the door, window, and trim project from last year. We are very excited about this improvement.
PA/Clock System
The replacement of PA/Clock systems at Franklin Elementary Schools is currently underway. This will provide a better internal system to communicate with the school and students, especially improve safety communications in an emergency. The new PA/clock systems will be combined in a single set of hardware devices. This system provides improved paging functionality and a new ability to post text messages useful for daily updates and during emergencies. Similar to other equipment, some of the devices that are critical to the completion of this project are suffering from longer lead times due to disruptions in the global supply chain. In order to reduce the overall impact to students and school staff, we are currently working on the installation of conduit, wiring and other related infrastructure. Once all the devices have arrived at the site, the team will work outside of normal school hours to complete their installations. The existing PA/Clock systems at Franklin ES will remain functional until the new systems are complete and functional.
Security Cameras
Security cameras have been fully installed, programmed and staff has been trained in the operation of the security system. Security cameras are located around the perimeter of the campus and outdoor areas. They will support increased safety and property management.
Elevator
The Elevator Controller, elevator doors and cables were replaced, and the new installation was inspected and passed by the State Elevator inspector on Monday 8/02/2021. This rehabilitates the elevator with better operations and increased safety.
Furniture
The district purchased new teacher/classroom furniture to go with the student desks purchased by the PTA a few years ago. This helps to make the classrooms more flexible to improve learning/teaching options. The classrooms have been prepared for students to return under the COVID-19 reopening protocols.
Asphalt
The Maintenance Department had a plan to repair and replace the asphalt in the play area in the back of the school. Due to contracting delays, this could not be completed this summer. It will be rescheduled for the winter break.
We are pleased to provide you with this modernization update and looking forward to a great start to the new school year!