Progress at JAMS PAC

Posted by Kelcey Davis on 1/15/2021 8:00:00 AM

Performing Arts Center 

When complete, the center, a joint project with Santa Monica College, will house a 750-seat theater, dedicated rehearsal space, choir room and more. 

JAMS PAC building stage area

Progress continues on the stage and seating area and on both levels of the building and back of building. Taping fo interior walls and ceilings, two restrooms are having tile work and fixtures installed. 

Painting and structual work is complted on the catwalk level. 

Rehersal Building

Scaffolding has been erected around the exterior of the rehersal building.

Sitewide

Sitewide, all utlities have been installed including gas, fire water, domestic water, sewer and storm drains.