Building G Abatement and Demolition Project
Posted by Kelcey Davis on 10/6/2021 7:00:00 AM
Abatement and demolition of Building G is 100% complete. Traces of PCBs were identified in the soil following demolition of the building. Export of the hazardous soil was completed on September 17, 2021. The remaining soil was tested and cleared. Rough grading of the Building G footprint started on September 24, 2021 and has been completed. Underground utilities are currently underway in preparation for the future Modular Village Project which will involve the relocation of four portable classrooms and one portable restroom from the former Juan Cabrillo Elementary School campus to the former Building G footprint. The relocation of portables will occur summer 2022.
View of the former Building G footprint looking southeast. Underground infrastructure going in.